water quality projects: slip-lining project

Slip-lining will take place in three phases: Phase 1, on Coronado Street from Sunset Blvd. to Bellevue, is slated to begin in late 2005 and be completed by late 2006. 

Phase 2 will run along Sunset from Coronado west to Parkman Avenue and is slated to begin in late 2006 and be completed in summer 2007.

Phase 3, if required, will run under Silver Lake Blvd. between Sunset and Effie Street, and is scheduled to start in late 2007 through summer 2008.